Moor Park Heritage Lottery Fund

Pound sign

For Phase 1 of the park restoration masterplan, a £2.35million scheme was developed and submitted to the Heritage Lottery Fund (HLF) for approval.

Phase 1 application

In June 2014, the HLF panel approved our Phase 1 application and awarded the Council with a Stage 2 pass. This resulted in a grant offer from HLF of £1,725,000.

The approved scheme estimate of £2.35 million included additional external match funding and the Council's own contributions totalling £0.625m above the £1.725m secured from the Heritage Lottery Fund.

The £0.625m included external funding of £90,000 plus additional works in kind of £35,000.

What did the phase 1 scheme consisted of?

  • refurbishment of the Grotto (and discovery of the lost cascade),
  • refurbishment of the Observatory,
  • refurbishment of the Changing Pavilion,
  • refurbishment of the Bowls Pavilions (including a new café),
  • installation of a skate park,
  • improvements to park infrastructure, paths and drainage,
  • major entrance improvements and boundary treatments,
  • historical horticultural restoration (including newly restored Decorative garden)
  • installation of new street furniture (seats and bins and signage),
  • improvements to existing trees,
  • additional tree planting.

The Phase 1 scheme will be fully complete by late summer 2018.

The masterplan for the park will not be finished until we can carry out a subsequent Phase 2 refurbishment project. This project will concentrate on upgrading the Serpentine Lake Area and also provide improved play facilities within the park.